Build times: Van's RV-10

Brendon's RV-10

Total Build Time
1043.4 hours

Avionics

Build time: 61.5 hours

in progress
50%

Firewall forward

Build time: 6 hours

in progress
15%

Engine

Build time: -

not started
0%

Fuselage

Build time: 412.3 hours

in progress
55%

Miscellaneous

Build time: 2.5 hours

not started
0%

Canopy

Build time: -

not started
0%

Electrical

Build time: 2.5 hours

in progress
50%

Painting

Build time: -

not started
0%

Upholstery

Build time: -

not started
0%

Tail

Build time: 303.5 hours

in progress
95%

Elevator

Build time: 68.8 hours

on hold
0%

Horizontal stabilizer

Build time: 64.3 hours

complete
100%

Rudder

Build time: 24 hours

on hold
0%

Vertical stabilizer

Build time: 23.6 hours

on hold
0%

Wings

Build time: 257.7 hours

in progress
5%

Ailerons

Build time: 19.3 hours

in progress
50%

Flaps

Build time: 52.8 hours

complete
100%

Main wing

Build time: 175.1 hours

in progress
80%

Section build times

Section Status Time
(hrs)
Progress
Avionics in progress 61.5
50%
Firewall forward in progress 6
15%
Engine not started - -
Fuselage in progress 412.3
55%
Miscellaneous not started 2.5 -
Canopy not started - -
Electrical in progress 2.5
50%
Painting not started - -
Upholstery not started - -
Tail in progress 303.5
95%
Elevator on hold 68.8 -
Horizontal stabilizer complete 64.3
100%
Rudder on hold 24 -
Vertical stabilizer on hold 23.6 -
Wings in progress 257.7
5%
Ailerons in progress 19.3
50%
Flaps complete 52.8
100%
Main wing in progress 175.1
80%
* If a parent section's time is greater than the sum of its sub-sections, it simply means one or more posts weren't categorized under a sub-section.

Build times by tag

Tag Build time (hrs)
horizontal stabilizer 51.8
Elevator 58.2
Wing 14.5
Tools 4.5
propeller 6
Priming 102.3
Match Drilling 46.4
Rough Assembly 6.8
Deburring 22.1
Dimpling 16.6
Control assembly 3.5
Trim 5.5
Wing Spars 30
Vertical Stabilizer and Rudder 1
Trim tab 7.1
Nutplates 7.3
Cleaning 7.9
Autopilot 7.5
Wings 22
Center Fuselage 18.5
leading edge 20.8
Drilling 25.5
Countersinking 37.9
Riveting 84
Torquing 2
Tailcone 66.1
Tie Down Bracket 7.3
Wing Ribs 9.8
Assembly 5

Build times by week