Build times: Van's RV-14

David's RV-14

Total Build Time
567.8 hours

Avionics

Build time: -

not started
0%

Firewall forward

Build time: -

not started
0%

Engine

Build time: -

not started
0%

Fuselage

Build time: 113.7 hours

in progress
5%

Miscellaneous

Build time: -

not started
0%

Canopy

Build time: -

not started
0%

Electrical

Build time: -

not started
0%

Painting

Build time: -

not started
0%

Upholstery

Build time: -

not started
0%

Tail

Build time: 193.1 hours

in progress
0%

Elevator

Build time: 75.6 hours

complete
5%

Horizontal stabilizer

Build time: 52.5 hours

complete
100%

Rudder

Build time: 45 hours

complete
100%

Vertical stabilizer

Build time: 12 hours

complete
100%

Wings

Build time: 261 hours

not started
0%

Ailerons

Build time: -

not started
0%

Flaps

Build time: -

not started
0%

Main wing

Build time: 261 hours

not started
0%

Section build times

Section Status Time
(hrs)
Progress
Avionics not started - -
Firewall forward not started - -
Engine not started - -
Fuselage in progress 113.7
5%
Miscellaneous not started - -
Canopy not started - -
Electrical not started - -
Painting not started - -
Upholstery not started - -
Tail in progress 193.1 -
Elevator complete 75.6
5%
Horizontal stabilizer complete 52.5
100%
Rudder complete 45
100%
Vertical stabilizer complete 12
100%
Wings in progress 261 -
Ailerons not started - -
Flaps not started - -
Main wing in progress 261 -
* If a parent section's time is greater than the sum of its sub-sections, it simply means one or more posts weren't categorized under a sub-section.

Build times by tag

Tag Build time (hrs)
empennage 10
vertical stabilizer 10
rudder 14
horizontal stabilizer 9.5
Wing cradle 7

Build times by week