Gary's Sling TSi

6 Apr 2026

Tail fairing installation & delivery of some parts for painting

Took the ailerons, flaps, rudder and wheel spats to the painter

Temporarily fitted the horizontal stabiliser, vertical stabiliser and then positioned the tail fairing in place. Drilled per the KAI, fitted M4 rivnuts with Loctite 277. Fitted the fairing cover for the ELT antenna

Filled and sanded some rivets on the wings, fuselage, and empennage

Fitted the BNC connected to the vertical stabiliser RG400 cable for the VOR antenna

Previous post:
21 Mar 2026

This post is from Gary's Sling TSi