Build times: Bearhawk Aircraft 4 Place

Neville's Bearhawk

Total Build Time
1729.7 hours

Avionics

Build time: 41 hours

complete
100%

Firewall forward

Build time: 444 hours

complete
100%

Engine

Build time: 254.5 hours

complete
100%

Fuselage

Build time: 530.8 hours

complete
100%

Miscellaneous

Build time: 72.5 hours

complete
100%

Electrical

Build time: -

complete
100%

Painting

Build time: 32 hours

complete
100%

Upholstery

Build time: 40.5 hours

complete
100%

Tail

Build time: 167 hours

complete
100%

Elevator

Build time: 16 hours

complete
100%

Horizontal stabilizer

Build time: 41 hours

complete
100%

Rudder

Build time: 54.5 hours

complete
100%

Vertical stabilizer

Build time: 55.5 hours

complete
100%

Wings

Build time: 409.8 hours

complete
100%

Ailerons

Build time: 24 hours

complete
100%

Flaps

Build time: 169.3 hours

complete
100%

Main wing

Build time: 56.5 hours

complete
100%

Section build times

Section Status Time
(hrs)
Progress
Avionics in progress 41
100%
Firewall forward in progress 444
100%
Engine in progress 254.5
100%
Fuselage in progress 530.8
100%
Miscellaneous complete 72.5
100%
Electrical complete -
100%
Painting complete 32
100%
Upholstery in progress 40.5
100%
Tail complete 167
100%
Elevator complete 16
100%
Horizontal stabilizer complete 41
100%
Rudder complete 54.5
100%
Vertical stabilizer complete 55.5
100%
Wings complete 409.8
100%
Ailerons complete 24
100%
Flaps complete 169.3
100%
Main wing complete 56.5
100%
* If a parent section's time is greater than the sum of its sub-sections, it simply means one or more posts weren't categorized under a sub-section.

Build times by tag

Tag Build time (hrs)
empennage 8
rudder 26
horizontal stabilizer 3
Elevator 19
Wing 7
Aft Fuselage 0.5
Fuselage 2
flaps 13.8
fuel system 25.8
brakes 47.3
firewall 16.5
engine 26
propeller 10
exhaust 19
cowl 3
avionics 70
Match Drilling 5
Rough Assembly 5
Cargo 5
Dimpling 11
Control assembly 28.5
Stringers 12.2
Skylight 26
Door sill 6
Boot cowl 94
Tunnel 14
Doors 138
Trim 6
Seats 25.6
Floor 18.6
Undercarriage 25
Instrument Panel 72
Wheels 15
Forward Fuselage 9
Fuel Lines and Valve Installation 30
Horizontal Stabilizer and Elevator 11
Horizontal Stabilizer and Elevators 12
Vertical Stabilizer and Rudder 10
Cockpit - Instrument Panel and Controls 18
Firewall Forward 111
Paint 112.5
Covering 110
Trim tab 5
Landing gear 4
Nutplates 2
NACA vents 4.5
Window 5.5
Aerial 1
Welding 6
Elt 6
Inspection ports 1.5
Fabrication of parts 3
Nose bowl 6
Cowls 50
Baffles 31
Upholstery 7
Flying -

Build times by week